Is it possible to sync Gantt charts?

If I have the same issues in multiple Gantt charts and I edit its duration or start time on a timeline, is it possible to sync this change to the other Gantt charts?

1 comment
Comment actions Permalink

Hi,

When you edit the duration and start times of issues on a Gantt chart, these changes are saved in the issues themselves. That means you will update the issue's duration and it will be reflected in its Estimation field. So each Gantt chart that displays this issue should be updated accordingly. Start dates behave similarly - if you set the Start date field in the Gantt chart settings, it will store each issue's start dates there. So each new Gantt chart will consider it too.

Please let me know if it works for you. 

0

Please sign in to leave a comment.