Can YouTrack create sprints based on existing Fix Versions?
I have manually defined several releases in my Fix Versions enumeration for a project. (e.g. "Week 1", "Week 2")
I have then assigned each issue to a release using the Fix Versions field.
Now I want to start using the Agile Board.
Creating a sprint in there just adds another value to my Fix Versions enumeration.
Is it possible to have YouTrack create sprints based on my existing Fix Versions field?
If I try to create a new sprint with the same name as the values in my Fix Versions field, e.g. "Week 1", it is blocked.
I don't want to have to create all the sprints and reassign all the bugs...
I have then assigned each issue to a release using the Fix Versions field.
Now I want to start using the Agile Board.
Creating a sprint in there just adds another value to my Fix Versions enumeration.
Is it possible to have YouTrack create sprints based on my existing Fix Versions field?
If I try to create a new sprint with the same name as the values in my Fix Versions field, e.g. "Week 1", it is blocked.
I don't want to have to create all the sprints and reassign all the bugs...
Please sign in to leave a comment.
The versions that already exist in the Fix version enumeration can be selected on the agile board when you click "Unscheduled" beneath the prject combo. See screenshot