I can no longer create a new sprint, the options have dissapeared
For whatever reason, I am no longer able to create a new Sprint on my board. Both the Create -> New Sprint option is missing, and so is the calendar popup.
How can I create new sprints?? I've confirmed all projects on the board have an Estimation and Fix Version field. Please see the screenshot
How can I create new sprints?? I've confirmed all projects on the board have an Estimation and Fix Version field. Please see the screenshot
Please sign in to leave a comment.
Did you check Agile settings> Change settings option? If still reproduce the case, ask your admin user to delegate you Update project permission (in case your board reflects several projects then Update project permission should be applied among all projects).
You should have admin permissions in projects which are reflected to the board and have these permissions under Agile settings> Change settings.
Under Administration> Users> your user> Permissions view check you have of the required for target projects (and provide me with the screenshot of your Permissions view page), then try to set Project based under Agile> Change settings.
I looked at Scott's suggestion, but could not understand his instruction "I removed all the existing values and created a new one via this interface."
Attached is a screenshot of my permission view page. I am still unable to Create new Sprints.
Have you recently archived a project that was used in your sprints? If you have, the problem is most likely that the Version field is in a bundle that is also used in the archived project.
What I did to solve this was to un-archive the project, move its Version field to a project-specific bundle, and then re-archive it.