View AgileBoard swimlanes by Project
Hi,
How do I separate tasks on the Agile board by project?
If I can create swimlanes per project then that would work. If there is any other way please let me know.
Thanks,
- Ani
How do I separate tasks on the Agile board by project?
If I can create swimlanes per project then that would work. If there is any other way please let me know.
Thanks,
- Ani
Please sign in to leave a comment.
First off, a board can be configured to reflect only one project(Agile settings> chose target project).
If the board reflects several projects, then you may filter swimlanes by project
As for creation, when report a swimlane, you should be offered to chose the project.
Thank you.
Thanks for your response.
However I am not able to see either of your answers in Agile Settings.
1. I do not see a "Choose Target Project" option in Agile Settings.
2. Swimlane creation – "Field to Identify Swimlane" also does not offer an option to choose the project.
So if you enter there "project: <project name>" and hit Ctrl-Enter, your Agile board will only show the swimlanes for that project.
And the other thing he means is, if you create a new swimlane, so you click on "create new swimlane", you then will be able to choose to which project this should belong to.
Currently, there is now way to Identify a swimlane by project, or group your swimlanes by project. At least as far as I know.