Move story and its tasks to sprint

Hi, new user here!

When assigning a story to a sprint, I noticed it does not move the story's tasks - so I must move them manually, one by one.

How do I move a story and its tasks as a group?

Thanks.

 
 
3 comments
Comment actions Permalink
Official comment

Hi! 

I'm Sergey from the Youtrack team. 

You can see an example of how you can implement this automatically in our instruction for Epic board: https://www.jetbrains.com/help/youtrack/incloud/Manage-Epics-on-Agile-Board.html 

In your case, though, it can just be User story → Tasks. The implementation will be similar. 

That's the best approach if you want to add issues to the board automatically. 

I hope this helps. 

Feel free to reply if you have any questions.


Also, if you'd like to get in touch with our support team directly for a quick answer to your question, please fill in a direct request at https://youtrack-support.jetbrains.com/hc/en-us/requests/ We'll be happy to help.

Comment actions Permalink

As a follow-up, you can also just add a bunch of tasks to the board using a command line with the following syntax: add Board <board name> <sprint name>. Please see the video example: https://take.ms/fuhHP 

This one works great when you add issues to the board manually. 

Hope this helps! 

0
Comment actions Permalink

I'm gonna try that. Thanks for the advice!

And thanks for the wonderful software!

 
 
0