Move story and its tasks to sprint

Hi, new user here!

When assigning a story to a sprint, I noticed it does not move the story's tasks - so I must move them manually, one by one.

How do I move a story and its tasks as a group?

Thanks.

 
 
0
3 comments
Official comment

Hi! 

I'm Sergey from the Youtrack team. 

You can see an example of how you can implement this automatically in our instruction for Epic board: https://www.jetbrains.com/help/youtrack/incloud/Manage-Epics-on-Agile-Board.html 

In your case, though, it can just be User story → Tasks. The implementation will be similar. 

That's the best approach if you want to add issues to the board automatically. 

I hope this helps. 

Feel free to reply if you have any questions.


Also, if you'd like to get in touch with our support team directly for a quick answer to your question, please fill in a direct request at https://youtrack-support.jetbrains.com/hc/en-us/requests/ We'll be happy to help.

As a follow-up, you can also just add a bunch of tasks to the board using a command line with the following syntax: add Board <board name> <sprint name>. Please see the video example: https://take.ms/fuhHP 

This one works great when you add issues to the board manually. 

Hope this helps! 

0
Avatar
Permanently deleted user

I'm gonna try that. Thanks for the advice!

And thanks for the wonderful software!

 
 
0